Skanska

Skanska purchased part of a large 72 Bay 3 storey modular building complex from Excel Modular in May 2015 and asked us to relocate the building to a new project site they where starting at Papworth Hospital, Cambridge

48 Modules where purchased in total in a “as is” condition and relocated to the new site, where alterations and improvements where carried out in June 2015.

Area: 1555m2

Start Date: 01/06/2015

Completion Date: 31/07/2015

Value: £500k

Mr Johnson was highly delighted in purchasing a pre-used modular building as they had saved 50% should they have purchased a new modular building.

“You’ve been a pleasure to work with, previous experience of the other modular companies have been a little to be desired o it’s a refreshing change!”